Prepare for the Permit Technician Test with comprehensive quiz questions and hints. Each question is designed to help you understand concepts clearly and increase your confidence for the exam. Start your preparation now!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is not typically included on a foundation plan?

  1. Height of foundation walls

  2. Finished roof elevation

  3. Location of piers

  4. Footing details

The correct answer is: Finished roof elevation

The finished roof elevation is typically not included on a foundation plan because a foundation plan primarily focuses on the elements that support the structure at its base level. The foundation plan shows how the building will be anchored to the ground, detailing aspects like the height of foundation walls, the location of piers, and the specifications of footings, which are crucial for the structural integrity of the building. The finished roof elevation, on the other hand, pertains to the design of the uppermost part of the building and is usually illustrated in a different part of the architectural plans, such as the elevation drawings. Elevation drawings provide a side view of the building as it will appear once completed, showing the roofline, materials, and heights above the foundation level. Therefore, it does not belong in the foundation plan, which is focused on sub-surfaces and ground-level considerations.